Hess Reports 4Q:21 Results, Updates on Guyana [PDF Download]

Instant Max AI

(Hess, 26.Jan.2022) — Hess Corporation (NYSE: HES) reported net income of $265mn, or $0.85 per share, in the fourth quarter of 2021, compared with a net loss of $97mn, or $0.32 per share, in the fourth quarter of 2020. On an adjusted basis, the corporation reported a net loss in the prior-year quarter of $176mn, or $0.58 per share. The improvement in adjusted after-tax results compared with the prior-year period was primarily due to higher realized selling prices in the fourth quarter of 2021.

“This year marks an inflection point in the execution of our strategy,” CEO John Hess said. “We have built a differentiated portfolio offering a unique value proposition – delivering durable cash flow growth that enables us to continue to invest in some of the highest return projects in the industry and to start growing our cash returns to our shareholders.”

Guyana (Offshore)

At the Stabroek Block (Hess – 30%), the operator, Esso Exploration and Production Guyana Limited, announced two significant discoveries at Fangtooth and Lau Lau. The Fangtooth-1 well encountered approximately 164 feet of high quality oil bearing sandstone reservoirs, and confirms the deeper exploration potential of the Stabroek Block. The well was drilled in 6,030 feet of water and is located approximately 11 miles northwest of the Liza Field. The Lau Lau-1 well encountered approximately 315 feet of high quality hydrocarbon bearing sandstone reservoirs. The well was drilled in 4,793 feet of water and is located approximately 42 miles southeast of the Liza Field.

The corporation’s net production from the Liza Destiny floating production, storage and offloading vessel (FPSO) was 31,000 bopd in the fourth quarter of 2021 compared with 26,000 bopd in the prior-year quarter.

On October 25, 2021, the Liza Unity FPSO, with an expected capacity of 220,000 gross bopd, arrived at the Stabroek Block and startup of Phase 2 of the Liza Field development remains on track for the first quarter of 2022.

The third development, Payara, will utilize the Prosperity FPSO with an expected capacity of 220,000 gross bopd; first oil is expected in 2024.

A fourth development, Yellowtail, was submitted to the government of Guyana for approval in the fourth quarter. Pending government approval and project sanctioning, the project is expected to have a capacity of 250,000 gross bopd with first oil anticipated in 2025.

“We expect to have at least six FPSOs on the Stabroek Block in 2027, with the potential for up to 10 FPSOs to develop the current discovered recoverable resource base. Following the completion of the Fangtooth-1 well, the Stena DrillMAX will begin drilling at the Tarpon prospect,” Hess said.

Following the completion of the Lau Lau-1 well, the Noble Don Taylor began drilling at the Barreleye prospect. The Stena Carron completed drill stem tests on the Longtail-2, Whiptail-2 and Turbot-2 wells, and is currently performing a drill stem test on the Tilapia-1 well. The Noble Sam Croft, the Noble Bob Douglas and the Noble Tom Madden are currently drilling and completing development wells at Liza Phase 2 and the Payara Field.