(SBM Offshore, 10.Feb.2022) — SBM Offshore provided a status update on individual projects from Guyana to Brazil.
Guyana
FPSO Liza Destiny
The third stage flash gas compressor on the unit remains stable and continues to operate. Additional engineering activities are ongoing to finalize a redesigned flash gas compressor with an expected installation on the unit around mid-year 2022.
FPSO Liza Unity
The FPSO Liza Unity arrived safely in Guyana in October 2021 where the hook-up and the installation campaigns have successfully been completed. Operations readiness activities have progressed and the project targets first oil in the first quarter of 2022.
FPSO Prosperity
The work in dry dock is progressing per schedule with the installation of the mooring systems. The topsides module fabrication is ongoing with the first modules planned to be completed and lifted in the first quarter of 2022. First oil is expected in 2024.
Brazil
FPSO Sepetiba
The modules fabricated in Brazil have arrived at the yard in China. The topsides module fabrication in China is progressing. The project targets first oil in 2023.
FPSO Almirante Tamandaré
The topsides fabrication has started in all yards. Both topsides fabrication and hull are progressing as planned. The project continues to target first oil in the second half of 2024.
FPSO Alexandre de Gusmão
The construction of the Fast4Ward® MPF hull and the procurement of equipment are well under way. The FPSO construction is progressing as per plan with expected first oil in 2025. Fast4Ward® MPF hulls. The six MPF hulls ordered to date under the company’s Fast4Ward® program have been allocated to projects. Four hulls have been delivered and the remaining two are under construction.