Construction of Francisco Pérez Ríos power plant progresses in Hidalgo 

MONTERREY, MEXICO (By Isaac Silvestre, Editores Latin Petroleum, 5.Nov.2026, Words: 121) — Construction of the Francisco Pérez Ríos combined cycle power plant in the state of Hidalgo is progressing.

The first concrete pour for the main air condenser structure was successfully completed, with 652 cubic meters of concrete poured during 11 hours of continuous work, the CFE announced on 5 Nov. 2026 in an official statement. 

“Thanks to the effort and coordination of our teams, we continue to take important steps to strengthen Mexico’s electrical infrastructure and energy generation capacity,” the CFE said. 

____________________

By Isaac Silvestre reporting from Monterrey. © 1999-2026 Energy Analytics Institute (EAI) and its 100% owned Venezuelan affiliate Editores Latin Petroleum CA. All Rights Reserved.

NOTE: photos courtesy of CFE.