MONTERREY, MEXICO (By Isaac Silvestre, Energy Analytics Institute, 27.Jul.2026, Words: 300) — One of Sempra Infrastructure‘s key priorities is completion of the ECA LNG Phase 1 project, a 1-train natural gas liquefaction facility in Ensenada, Mexico.
RELATED: SEMPRA INFRASTRUCTURE EXTENDS COMMISSIONING PROCESS OF ECA LNG PHASE 1 PROJECT
The project achieved mechanical completion in Dec. 2025 and introduced feed gas into the facility in Apr. 2026.
Moreover, the project achieved first liquefied natural gas (LNG) production as part of the commissioning process in Jun. 2026 and loaded and shipped its first cargo earlier this month.
RELATED: SEMPRA EXPECTS TO CLOSE ECOGAS MÉXICO DEAL IN AUG. 2026
____________________
By Isaac Silvestre reporting from Monterrey. © 1999-2026 Energy Analytics Institute (EAI). All Rights Reserved.