(Energy Analytics Institute, 14.Jun.2024) — New Fortress Energy (NFE) updated the timing of its first LNG expectation for its first Fast LNG unit located offshore Altamira, Mexico. The company has made tremendous progress on its path towards the start of liquefaction operations, it said 14 Jun. 2024 in an official statement.
“As of today, the work necessary to begin operations is complete and the company has also completed the full remainder of pre-commissioning activities. The company now expects to produce LNG in the next 10 days, and then expects to be able to deliver its first cargo in July [2024],” NFE said in the statement.