Wison Delivers Stick Batches to RPLC Project

Instant Max AI Immediate Frontier

(Wison Offshore & Marine Ltd., 21Apr.2015) – Wison Offshore & Marine Ltd. announced the delivery of its first batch of stick built for the key modularized components construction of the Petroleos De Venezuela, S.A.(PDVSA) Puerto La Cruz refinery project, achieving an important project milestone which demonstrated the strong capabilities of Wison Offshore & Marine in module fabrication.

“We’re quite confident in the on-time and quality delivery of the entire project,” said Mr. An Wenxin, Senior Vice President of Wison Offshore & Marine.

This is part of the contract awarded by HyundaiWison consortium (a consortium of Hyundai Engineering & Construction Co. Ltd., Hyundai Engineering Co., Ltd. and Wison Engineering Ltd.) to supply key modularized components including pipe racks and equipment modules. Under the contract, Wison Offshore & Marine is responsible for the shop drawing, material procurement, construction, precommissioning and load out.

There are altogether 94 modules and stick built totaling about 22,840 tonnes, which are to be delivered in 10 batches. While the first batch of stick built had been delivered, the module assembly has already commenced on 15.Mar.2015 at the same time and the first batch of modules shall deliver in Jul.2015 followed by progressive delivery with an interval of 1 month per shipment. The entire project shall complete in the 1H:16 as requested by the clients.

***

Previous post Baker Hughes Announces 1Q:15 LatAm Results
Next post Petrobras Reports Audited Results for 2014

Leave a Reply

Your email address will not be published.