RIO DE JANEIRO, BRAZIL (By Brava, 2.Jul.2026, Words: 191) — Brava Energia S.A. reported preliminary and unaudited production data for the month of Jun. 2026.
Potiguar
The company continues the gradual resumption of operations at its facilities in the Potiguar basin. The increase in oil production recorded in June reflects the progress of this process, particularly at the Fazenda Belém and Areia Branca clusters.

Papa-Terra
The asset will undergo a scheduled maintenance shutdown of up to 12 days during the second half of Jul. 2026. Originally planned for the fourth quarter 2026 (4Q26), the intervention has been brought forward to align maintenance activities with the drilling campaign currently underway.
This measure is intended to ensure that the asset is fully prepared to receive production from the two new wells (PPT-52 and PPT-53) immediately upon completion of the campaign.

Brava reiterates that the drilling campaign continues to progress in line with the original schedule and budget.
Brava operates the Potiguar, RecĂ´ncavo, Papa-Terra, Atlanta, and Peroá assets, and also holds a non-operated 35% stake in Pescada, 45% in the Manati Field, both operated by PETROBRAS, and 23% in Parque das Conchas, operated by Shell.Â

____________________