(Energy Analytics Institute, 27.Sep.2024) — CNOOC Limited said the Shenhai-1 Phase II Natural Gas Development Project has commenced production.
The project is located in the Qiongdongnan Basin, northern South China Sea, with an average water depth of approximately 900 m, CNOOC said 27 Sep. 2024 in an official statement.
The main production facilities include a new fixed production platform and 3 centralized subsea wellheads, with 12 development wells planned to be commissioned. It is expected to reach peak production of 162 million cubic feet of natural gas and 3,931 barrels of condensate per day in 2025.
“The project has successfully overcome the world-class challenge of deep-water high-pressure oil and gas reservoir development. It witnesses effective large-scale conversion of reserves into production from the ‘South China Sea trillion-cubic-meters-level gas region’, and provides stable supply of clean energy for the economic and social development of South China,” CNOOC chairman Wang Dongjin said in the statement.
“In the future, CNOOC Limited will accelerate the development of new quality productivity of marine energy, and strengthen the exploration and development of deep-water oil and gas resources, thereby further contributing to the high-quality development of China’s offshore oil industry,” Dongjin said.
CNOOC Limited holds 100% interest in this project and is the operator.
____________________
By Editors at Energy Analytics Institute. © Energy Analytics Institute (EAI). All Rights Reserved.